GMH Solutions

SERP SiteVault

Stakeholder-facing Site Documentation Vault for the Southern Electrical Rectification Projectacross six Cape hospital sites, combining site records, photo evidence, compliance registers, permits, visitors, and inductions.

Controlled Simpro mirror

Operational records only. Commercial data remains private to GMH.

Sync status: Timeline Drafts Imported

Hospital Sites

6

Mapped Simpro Sections

6

Published Records

80

Photo Evidence Items

216

Vault Register Items

53

Risk / Permit Items

0

Visitor / Induction Items

46

Visitor Sign-In

Open and print the hospital QR codes for visitor and subcontractor sign-in.

Visitor QR Codes

Project Documentation Vault

Compliance and register coverage

Project-wide read-only summary of stakeholder-safe documentation registers. Sensitive visitor contact details, licence documents, internal notes, and commercial information remain restricted to GMH.

SWMS / JSA / Compliance

6

Approved and submitted compliance documents across all sites.

Disruption Notices

1

Planned disruption records visible to stakeholders.

Risk / Permit Records

0

High-risk work, working-at-heights, and isolation permit items.

Visitors / Inductions

46

Stakeholder-safe visitor and induction summaries.

SiteComplianceDisruptionsHigh RiskHeightsIsolationsVisitorsInductionsOpen

Aurukun

5 vault records loaded

1000040View vault →

Weipa

2 vault records loaded

1100000View vault →

Napranum

42 vault records loaded

10000410View vault →

Lockhart River

1 vault records loaded

1000000View vault →

Laura

1 vault records loaded

1000000View vault →

Hope Vale

2 vault records loaded

1000010View vault →

Delivery Sequence

Hospital Site Records

Each site page is loaded from the SERP database and is now mapped to safe Simpro section metadata.

Recent Site Records

Latest published stakeholder-visible records from the local SERP database.

DateSiteRecordStatus
26 Aug 2026Napranum0630 Arrive at site. Sign in. Complete JSA. Check actual layout of rooms against plans and make notes. 1000 Smoko. 1015 Continue making notes. Attempted to pre-wire dental Clinic. Discovered walls to contain noggins and lack of 2.5mm2 cable. Unable to continue. 1300 Lunch. 1330 Install cabling (remaining SWA and some existing circuits. Discussed cutting trip short with Greg. Confirmed. Pack up/clean up. Stored remaining materials in site shed. Sign out. Complete job notes. 1630 Finish. Materials: NAPublished
26 Aug 2026Aurukunsign in - JSA and prestart - completed works, labelled and test and commissioed consult room 4 - completed works in consult 3, labelled, tear and commissioned - walked through site with Kris and the others - they requested to view the following: cable tray in a few locations, MDB-1, DB-A&B, several rooms new LPDs and GPOs, generator shed/area, several of the houses and their switchboards and generator pads, the BMS board in the hospital and out at the house generators, as well as the nurses quarters and DSB2&3 area. - began work on cleaners circuit. Identified current first point in circuit to changeover to new circuit and LPD for easier work next attendance - prepped maternity room for next visit - re mounted bat section above MSB - completely packed away trailer and materials for onsite - tidied SWB room and walked through entire hospital to ensure everything was clean, ceiling tiles were all close and all circuits were energised - signed out and completed notes Materials: - 1x LPD - 5x medilec GPO - 1x mounting block - 1/2 length of 20x10 duct - fixings - 1x blank plates - 9x bps - 2x jboxPublished
26 Aug 2026AurukunAurukun Hospital – Electrical WorksPublished
25 Aug 2026Napranum0630 Arrive at site. Sign in. Conplete JSA. Install cabling (P16,17,18). 0950 Smoko. 1005 Install cabling 1045 Meeting with Adrian to discuss future works. 1115 Tie-in run cables to ensure neatness. 1300 Lunch. 1330 Install cabling (P19,20, 21, P1). Tie-in run cables. 1600 Pack up/clean up. Sign out. Complete job notes. 1630 Finish. Materials: NAPublished
25 Aug 2026Aurukunsign in - JSA and prestart - complete testing of submains to DSB2, DSB3 and Nurses Quarters. - relabel cabling and schedule - visit council depot regarding spare wheels for generator trailer and sort out with Adrian - complete works in pathology - labelled new pathology - test and commissioned new p6 pathology circuit - begin works in consult 2 - alternate wiring to plans - 2x GPOs at height above windows bp'd in wall and blank plate installed as per instruction - existing LPD circuit isolated at LPD and all GPOs replaced with new medilec GPO - installed new LPD circuit, duct to LPD and 3x new GPOs as per plans - completed labelling of new and old circuit - test and commission p7 new LPD circuit in consult 2 - go through list of remaining works for Adrian - went through scheduling for next swing and confirmed most convenient dates for distributions with DON and other staff - tidied up outside and packed away gear, removed items and stored behind security fence - signed out and completed notes Materials: - 2x LPD - 9x medilec GPO - 6x mounting block - 1 length 20x10 duct - 1/2 length of 20x40 duct - fixings - 3x blank plates - 9x bpsPublished